职业道德与合规 中等 Business Environment 商业环境域 题号 PMP202611-030

题目

在回顾会议上,团队成员似乎不愿讨论失误。项目经理应该怎么做?
During a retrospective, team members seem hesitant to discuss mistakes. What should the project manager do?

选项

  1. A.Cancel the retrospective session
  2. B.Create a safe environment for open discussion
  3. C.Report the lack of participation to the functional manager
  4. D.Ask specific individuals to explain what went wrong
正确答案:B

解析

解析:心理安全感是有效回顾会议的前提。项目经理应鼓励坦诚反馈,而不追究个人责任。 Rationale:Psychological safety is essential for effective retrospectives. The project manager should encourage open and honest feedback without blame.