题目
项目为期九个月,已进行六个月却落后至少三个月,原因是若干关键相关方对重大变更持抵触态度。规划阶段本可以怎样做以避免?
A project is six months into a nine-month duration and is at least three months behind because certain key stakeholders were resistant to consequential changes. What might have been done differently during planning to avoid this?
选项
- A.Better execution of the Manage Stakeholder Engagement process
- B.Development of a stakeholder engagement assessment matrix
- C.Creation of a comprehensive stakeholder register
- D.Establishment of a more robust communications management plan
解析
解析:题干限定“规划阶段”。相关方参与评估矩阵能显示期望与当前参与度的差距,从而提前化解抵触;管理相关方参与属于执行。
Rationale:The question asks specifically about planning-phase actions; the engagement assessment matrix identifies desired vs. current engagement so resistance can be addressed proactively. Managing engagement is execution.