相关方分析与权力利益方格 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-637

题目

项目为期九个月,已进行六个月却落后至少三个月,原因是若干关键相关方对重大变更持抵触态度。规划阶段本可以怎样做以避免?
A project is six months into a nine-month duration and is at least three months behind because certain key stakeholders were resistant to consequential changes. What might have been done differently during planning to avoid this?

选项

  1. A.Better execution of the Manage Stakeholder Engagement process
  2. B.Development of a stakeholder engagement assessment matrix
  3. C.Creation of a comprehensive stakeholder register
  4. D.Establishment of a more robust communications management plan
正确答案:B

解析

解析:题干限定“规划阶段”。相关方参与评估矩阵能显示期望与当前参与度的差距,从而提前化解抵触;管理相关方参与属于执行。 Rationale:The question asks specifically about planning-phase actions; the engagement assessment matrix identifies desired vs. current engagement so resistance can be addressed proactively. Managing engagement is execution.

同考点练习题