相关方分析与权力利益方格 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-378

题目

相关方登记册中原被列为“低关注、低影响”的某相关方近期升职,现在对项目拥有重要决策权。项目经理应该怎么做?
A stakeholder who was previously classified as "low interest, low influence" on the stakeholder register has recently been promoted and now has significant decision-making authority over the project. What should the project manager do?

选项

  1. A.Immediately update the stakeholder register and engagement plan to reflect their new influence level, prioritise a relationship-building meeting, and ensure they receive appropriate communication going forward.
  2. B.Continue with the existing engagement plan: changing it mid-project creates confusion.
  3. C.Ask the original high-influence stakeholders to brief the newly promoted individual.
  4. D.Update the stakeholder register at the next scheduled review.
正确答案:A

解析

解析:A 正确。相关方登记册是活文档,相关方动态变化时必须更新,尤其是升职导致权力关系改变。此前沟通极少的新晋高影响相关方容易感到被忽视,反而成为阻力。必须立即更新并主动接触。等到定期评审(D)会留下关系空档;一成不变(B)无视实质变化;让别人代讲(C)过于被动,也未必能让新决策者得到准确图景。 Rationale:A is correct. Stakeholder registers are living documents that must be updated when stakeholder dynamics change, especially promotions that shift power relationships. A newly influential stakeholder who has been receiving minimal communication may feel excluded and become an obstacle. Immediate update and proactive engagement is required. Waiting for a scheduled review (D) creates a relationship gap. Continuing unchanged (B) ignores a material change. Delegating to other stakeholders (C) is passive and may not give the new decision-maker an accurate picture.