题目
项目经理发现某个工作包已完成,但客户从未正式验收。项目现在已经推进了两个阶段。风险是什么,项目经理应如何处理?
A project manager discovers that a work package was completed but never formally accepted by the client. The project is now 2 phases ahead. What is the risk and what should the project manager do?
选项
- A.Document the gap in the lessons learned register and continue the project.
- B.The risk is that the client may later claim the work was not accepted and reject it. Obtain formal written acceptance now, even retrospectively, before more deliverables build upon unaccepted work.
- C.There is no risk: the work was completed successfully.
- D.Redo the work package to give the client a formal opportunity to accept it.
解析
解析:B 正确。正式验收是合同与治理要求,没有验收,交付物就没有正式地位。在未验收的基础上继续推进后续阶段风险很大:一旦后期被拒收,多个阶段都可能要付出高昂返工。补办书面验收正是堵住缺口。把“完成”等同于“验收”(C)不成立;只写经验教训(A)解决不了当下风险;重做(D)没有必要——成果已完成,缺的只是正式签认。
Rationale:B is correct. Formal acceptance is a contractual and governance requirement: without it, the deliverable has no official status. The risk of building further phases on unaccepted foundational work is significant: a late rejection could require costly rework of multiple phases. Obtaining retrospective written acceptance closes the gap. Assuming completion equals acceptance (C) is incorrect. Lessons learned (A) doesn't fix the current risk. Redoing work (D) is unnecessary, the deliverable is complete; only formal sign-off is missing.
同考点练习题
-
PMP202611-185 · 答案 B
-
PMP202611-438 · 答案 C
-
PMP202611-549 · 答案 B
-
PMP202611-558 · 答案 A
-
PMP202611-650 · 答案 C