完工尚需绩效指数(TCPI)的公式是什么?TCPI 为 1.2 意味着什么?
What is the To-Complete Performance Index (TCPI) formula and what does a TCPI of 1.2 mean?
选项
- A.TCPI = (BAC − EV) ÷ (BAC − AC). A TCPI of 1.2 means the remaining work must be done at 120% efficiency relative to the original plan: very challenging.
- B.TCPI = EV ÷ AC. A TCPI of 1.2 means the project is 20% over budget.
- C.TCPI = (BAC − EV) ÷ (EAC − AC). A TCPI of 1.2 means the project is ahead of schedule.
- D.TCPI = BAC ÷ CPI. A TCPI of 1.2 means the project needs 20% more budget.
解析
解析:A 正确。TCPI =(BAC − EV)÷(BAC − AC),衡量剩余工作要达到原预算(BAC)所需的成本效率。TCPI 为 1.2 表示剩余工作必须按计划效率的 120% 完成,远难于当前 CPI 水平;TCPI 超过 1.1 通常被视为不现实,说明 BAC 可能需要修订。B 描述的是 CPI,D 描述的是 EAC。
Rationale:A is correct. TCPI = (BAC − EV) ÷ (BAC − AC). It measures the cost efficiency required on remaining work to meet the original budget (BAC). A TCPI of 1.2 means the team must perform at 120% of planned efficiency for the rest of the project: significantly harder than the current CPI. A TCPI above 1.1 is generally considered unrealistic, suggesting the BAC may need to be revised. Option B describes CPI. Option D describes EAC.