完工预测:EAC/ETC/TCPI/VAC · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-504

题目

若项目 TCPI 为 1.15,说明:
If a project's TCPI is 1.15, it means:

选项

  1. A.The project is 15% over budget
  2. B.The schedule is 15% behind
  3. C.Costs are 15% under budget
  4. D.The team must achieve 15% greater cost efficiency than planned to meet the goal
正确答案:D

解析

解析:TCPI 大于 1 表示剩余工作必须比原计划更省才能达标。 Rationale:TCPI > 1 means future cost performance must be more efficient than planned to hit the target.