若项目 TCPI 为 1.15,说明:
If a project's TCPI is 1.15, it means:
选项
- A.The project is 15% over budget
- B.The schedule is 15% behind
- C.Costs are 15% under budget
- D.The team must achieve 15% greater cost efficiency than planned to meet the goal
解析
解析:TCPI 大于 1 表示剩余工作必须比原计划更省才能达标。
Rationale:TCPI > 1 means future cost performance must be more efficient than planned to hit the target.