能力缺口与培训 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-638

题目

某需要多种编程语言的软件项目中,一名开发被职能经理抽调走,改派另一名开发替代。你首先应当做什么?
On a multilingual software project, a developer is pulled out by her functional manager and replaced by another developer. What should you do first?

选项

  1. A.Provide the new developer with an ability test
  2. B.Introduce the new developer to the project sponsor
  3. C.Schedule training for the new developer
  4. D.Assign the developer the next user story in the backlog
正确答案:A

解析

解析:能力测试这类个人评估工具能揭示优势与短板,先弄清能力状况,再决定是培训还是直接分派工作。 Rationale:Individual assessment tools such as ability tests reveal strengths and weaknesses, letting you decide whether training or a different assignment is needed before allocating work.