题目
某需要多种编程语言的软件项目中,一名开发被职能经理抽调走,改派另一名开发替代。你首先应当做什么?
On a multilingual software project, a developer is pulled out by her functional manager and replaced by another developer. What should you do first?
选项
- A.Provide the new developer with an ability test
- B.Introduce the new developer to the project sponsor
- C.Schedule training for the new developer
- D.Assign the developer the next user story in the backlog
解析
解析:能力测试这类个人评估工具能揭示优势与短板,先弄清能力状况,再决定是培训还是直接分派工作。
Rationale:Individual assessment tools such as ability tests reveal strengths and weaknesses, letting you decide whether training or a different assignment is needed before allocating work.
同考点练习题
-
PMP202611-279 · 答案 B
-
PMP202611-443 · 答案 B
-
PMP202611-584 · 答案 D
-
PMP202611-636 · 答案 B
-
PMP202611-660 · 答案 B