团队建设与团队章程 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-161

题目

团队已约定会议中不打断他人。但有一名成员屡屡打断别人,其他成员明显感到沮丧。最好的做法是什么?
The team agreed not to interrupt each other in meetings. One member keeps interrupting, and others look frustrated. What is the best approach?

选项

  1. A.Remove the member from meetings.
  2. B.Remind the team of its working agreement and encourage the team to hold each other to it.
  3. C.Ignore it because the member is a high performer.
  4. D.Rewrite the working agreement yourself.
正确答案:B

解析

解析:工作协议属于团队。提醒全体并支持团队自己执行规则,才能建立健康文化;放任不管会削弱协议的效力。 Rationale:Working agreements belong to the team. Reminding everyone and supporting the team to enforce its own rules builds a healthy culture; ignoring the behaviour weakens the agreement.