题目
公司将在下个月把团队切换到新的云端测试工具,多数成员从未使用过。你首先应该做什么?
Your organisation is moving the team to a new cloud testing tool next month. Most team members have never used it. What should you do first?
选项
- A.Delay the tool until the project ends.
- B.Assess the team's skill gaps and plan training before the switch.
- C.Let team members learn on the job.
- D.Hire external testers who know the tool.
解析
解析:先评估差距并规划培训是主动做法,可降低工具上线时的延误风险。招聘外部人员可以是后续选项,但不是第一步。
Rationale:Assessing gaps and planning training is the proactive choice. It reduces the risk of delays when the tool goes live. Hiring outsiders may be an option later, but it is not the first step.