资源管理 困难 People 人域 题号 PMP202611-636

题目

团队绩效评估暴露出此前未知的技术能力短板,需要弥补。下一步应当做什么?
A team performance appraisal uncovers a previously unknown competency gap in technical skills that needs to be addressed. What should you do next?

选项

  1. A.Implement the response planned for this risk
  2. B.Conduct unplanned training to address the competency gap
  3. C.Consult the training management plan
  4. D.Let go of the staff who have technical skill gaps
正确答案:B

解析

解析:评估才发现的能力缺口不可能预先写进计划,因此需要计划外培训——这类培训正是源于观察、沟通与绩效评估。 Rationale:A gap discovered via appraisal cannot be in the plan, so it requires unplanned training, which arises from observation, conversation and performance appraisals during team management.