风险管理计划与过程 · PMP 练习题解析

风险管理 困难 Process 过程域 题号 PMP202611-618

题目

旧办公楼改造中,部分水管外包有石棉保温层。考虑楼龄,这本是已知风险,应对计划是请专业清除公司处理。清除完成后,团队发现部分水管出现腐蚀。项目经理首先应当做什么?
During renovation of an old office building, asbestos insulation is discovered on some plumbing pipes. Given the building's age this was a known risk; the response calls for a specialized remediation contractor. After remediation, the team finds corrosion in some pipes. What should the PM do first?

选项

  1. A.Request the remediation company make the repairs since the corrosion was detected during their work
  2. B.Capture the information in the issue log and assign a responsible party to ensure the issue is tracked and resolved
  3. C.Document to the risk register corrosion as a secondary or residual risk and implement the agreed-upon risk response plan
  4. D.Update the lessons learned register to ensure that risk planning for similar future projects should be performed more thoroughly
正确答案:B

解析

解析:实施风险应对时暴露出的腐蚀属于“问题”,应记入问题日志并指定责任人跟踪解决。 Rationale:Implementing risk responses surfaced the corrosion as an issue; issues identified during that process are recorded in the issue log with an owner for tracking and resolution.

同考点练习题