旧办公楼改造中,部分水管外包有石棉保温层。考虑楼龄,这本是已知风险,应对计划是请专业清除公司处理。清除完成后,团队发现部分水管出现腐蚀。项目经理首先应当做什么?
During renovation of an old office building, asbestos insulation is discovered on some plumbing pipes. Given the building's age this was a known risk; the response calls for a specialized remediation contractor. After remediation, the team finds corrosion in some pipes. What should the PM do first?
选项
- A.Request the remediation company make the repairs since the corrosion was detected during their work
- B.Capture the information in the issue log and assign a responsible party to ensure the issue is tracked and resolved
- C.Document to the risk register corrosion as a secondary or residual risk and implement the agreed-upon risk response plan
- D.Update the lessons learned register to ensure that risk planning for similar future projects should be performed more thoroughly
解析
解析:实施风险应对时暴露出的腐蚀属于“问题”,应记入问题日志并指定责任人跟踪解决。
Rationale:Implementing risk responses surfaced the corrosion as an issue; issues identified during that process are recorded in the issue log with an owner for tracking and resolution.