题目
你即将为一个规模大、涉及法规与环境因素、需要详尽计划的复杂项目做规划。作为初始规划的起点,第一件事应当做什么?
You are about to start planning a large complex project with regulatory and environmental considerations, so a detailed plan will be critical. As a starting point for initial planning, what is the first thing you should do?
选项
- A.Conduct a project kick-off meeting to inform and engage stakeholders
- B.Review the project charter to understand the high-level information about the project
- C.Begin identifying stakeholders so they can be engaged for planning
- D.Share the project scope statement with the team for a common understanding
解析
解析:启动阶段形成的项目章程是初始规划的起点,它定义了后续计划要展开的高层信息。
Rationale:The project charter, created during initiation, is the starting point for initial planning; it defines the high-level information to be elaborated in the plan.