项目管理实践与流程 · PMP 练习题解析

知识管理与经验 中等 Business Environment 商业环境域 题号 PMP202611-605

题目

你即将为一个规模大、涉及法规与环境因素、需要详尽计划的复杂项目做规划。作为初始规划的起点,第一件事应当做什么?
You are about to start planning a large complex project with regulatory and environmental considerations, so a detailed plan will be critical. As a starting point for initial planning, what is the first thing you should do?

选项

  1. A.Conduct a project kick-off meeting to inform and engage stakeholders
  2. B.Review the project charter to understand the high-level information about the project
  3. C.Begin identifying stakeholders so they can be engaged for planning
  4. D.Share the project scope statement with the team for a common understanding
正确答案:B

解析

解析:启动阶段形成的项目章程是初始规划的起点,它定义了后续计划要展开的高层信息。 Rationale:The project charter, created during initiation, is the starting point for initial planning; it defines the high-level information to be elaborated in the plan.

同考点练习题