质量控制与检查 · PMP 练习题解析

质量管理 中等 Process 过程域 题号 PMP202611-601

题目

在测试把碎旧轮胎装入铁路货车的设备时,你发现地面散落大量碎轮胎,不确定是否允许有洒落。应当到哪里查这一信息?
While testing equipment that loads shredded recycled tires into railroad cars, you notice much shredded tire on the ground and are unsure whether any spillage is allowable. Where would you find this information?

选项

  1. A.Quality control plan
  2. B.Project management plan
  3. C.Quality report
  4. D.Quality policy
正确答案:B

解析

解析:质量管理计划是项目管理计划的组成部分,规定质量目标、标准与准则,其中包括是否允许洒落。 Rationale:The quality management plan, a component of the project management plan, sets quality objectives, standards and criteria — including whether spillage is allowed.