沟通技巧:倾听反馈与情商 · PMP 练习题解析

沟通管理 困难 Process 过程域 题号 PMP202611-514

题目

某相关方说“你就告诉我一切按计划就行”。而项目实际已落后三周。你应当:
A stakeholder says, 'Just tell me we're on track.' The project is actually 3 weeks behind. You should:

选项

  1. A.Say you're on track to keep them happy
  2. B.Communicate honestly with the revised forecast and recovery options
  3. C.Avoid the stakeholder
  4. D.Blame the team
正确答案:B

解析

解析:用事实加方案做诚实透明沟通才能维持信任,隐瞒坏消息最终一定反噬。 Rationale:Honest, transparent communication with facts and options preserves trust; hiding bad news always backfires.