题目
某相关方说“你就告诉我一切按计划就行”。而项目实际已落后三周。你应当:
A stakeholder says, 'Just tell me we're on track.' The project is actually 3 weeks behind. You should:
选项
- A.Say you're on track to keep them happy
- B.Communicate honestly with the revised forecast and recovery options
- C.Avoid the stakeholder
- D.Blame the team
解析
解析:用事实加方案做诚实透明沟通才能维持信任,隐瞒坏消息最终一定反噬。
Rationale:Honest, transparent communication with facts and options preserves trust; hiding bad news always backfires.
同考点练习题
-
PMP202611-044 · 答案 B
-
PMP202611-083 · 答案 B
-
PMP202611-159 · 答案 C
-
PMP202611-229 · 答案 B
-
PMP202611-283 · 答案 A
-
PMP202611-332 · 答案 B
-
PMP202611-374 · 答案 B
-
PMP202611-422 · 答案 A