管理相关方参与 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-506

题目

相关方参与评估矩阵显示某关键相关方目前“中立”,而你需要他“支持”。最佳做法是:
A stakeholder engagement assessment matrix shows a key stakeholder is currently 'neutral' but you need them 'supportive'. The BEST action is to:

选项

  1. A.Increase all project communications
  2. B.Remove them from distribution lists
  3. C.Develop a targeted engagement strategy addressing their specific concerns
  4. D.Wait until they become resistant
正确答案:C

解析

解析:该矩阵比较当前与期望参与度,需针对特定相关方制定定向策略才能推动其转变。 Rationale:The stakeholder engagement assessment matrix compares current vs. desired engagement; targeted strategies move specific stakeholders toward the desired state.