进度压缩与赶工 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-496

题目

项目必须提前两周完工。赶工需多花 8000 美元,快速跟进的重工风险 EMV 为 3000 美元。最佳选择是:
A project must finish two weeks early. Crashing adds $8,000 and fast-tracking adds $3,000 in rework risk (EMV). The BEST choice is:

选项

  1. A.Fast-track, because the EMV of rework is lower than the crashing cost
  2. B.Crash, because it is more reliable
  3. C.Do both to be safe
  4. D.Refuse the earlier date
正确答案:A

解析

解析:快速跟进的 3000 美元重工风险低于 8000 美元赶工成本,应选成本更低的进度压缩方式。 Rationale:Fast-tracking's $3,000 EMV rework risk is cheaper than $8,000 crashing cost; choose the lower-cost schedule compression option.