题目
项目必须提前两周完工。赶工需多花 8000 美元,快速跟进的重工风险 EMV 为 3000 美元。最佳选择是:
A project must finish two weeks early. Crashing adds $8,000 and fast-tracking adds $3,000 in rework risk (EMV). The BEST choice is:
选项
- A.Fast-track, because the EMV of rework is lower than the crashing cost
- B.Crash, because it is more reliable
- C.Do both to be safe
- D.Refuse the earlier date
解析
解析:快速跟进的 3000 美元重工风险低于 8000 美元赶工成本,应选成本更低的进度压缩方式。
Rationale:Fast-tracking's $3,000 EMV rework risk is cheaper than $8,000 crashing cost; choose the lower-cost schedule compression option.