进度压缩与赶工 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-107

题目

通过增加资源、以最小增量成本缩短项目工期的进度压缩技术是:
A schedule compression technique used to shorten project duration for the least incremental cost by adding resources is called:

选项

  1. A.Crashing
  2. B.Program evaluation and review technique (PERT)
  3. C.Precedence diagramming method (PDM)
  4. D.Fast tracking
正确答案:A

解析

解析:赶工通过为关键路径活动增加资源来缩短工期,通常成本增量最小,但可能增加成本与风险。快速跟进则是把活动并行而非增加资源。 Rationale:Crashing adds resources to critical path activities to shorten duration, usually at the least incremental cost, but may increase cost and risk. Fast tracking overlaps activities instead of adding resources.