题目
通过增加资源、以最小增量成本缩短项目工期的进度压缩技术是:
A schedule compression technique used to shorten project duration for the least incremental cost by adding resources is called:
选项
- A.Crashing
- B.Program evaluation and review technique (PERT)
- C.Precedence diagramming method (PDM)
- D.Fast tracking
解析
解析:赶工通过为关键路径活动增加资源来缩短工期,通常成本增量最小,但可能增加成本与风险。快速跟进则是把活动并行而非增加资源。
Rationale:Crashing adds resources to critical path activities to shorten duration, usually at the least incremental cost, but may increase cost and risk. Fast tracking overlaps activities instead of adding resources.
同考点练习题
-
PMP202611-005 · 答案 B
-
PMP202611-050 · 答案 C
-
PMP202611-177 · 答案 B
-
PMP202611-294 · 答案 C
-
PMP202611-496 · 答案 A