进度压缩与赶工 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-294

题目

项目经理需要把工期压缩 3 周。给关键路径任务加资源可行但昂贵;另有若干任务可通过在紧前任务完成前启动来实现重叠。应采用哪种技术?
A project manager needs to compress the schedule by 3 weeks. Adding resources to critical path tasks is possible but expensive. Several tasks can be overlapped by starting them before predecessor tasks are complete. Which technique should be used?

选项

  1. A.Crashing: add resources to critical path tasks to shorten their duration.
  2. B.Resource levelling: redistribute existing resources to balance workload.
  3. C.Fast-tracking: overlap tasks that would normally be done sequentially to compress the schedule.
  4. D.Scope reduction: remove deliverables to shorten the schedule.
正确答案:C

解析

解析:C 正确。题干描述的是快速跟进:在紧前任务完成前启动后续任务,会增加风险但不用额外成本就能缩短工期。赶工(A)靠加资源压缩工期,正是题干所说的昂贵方案;削减范围(D)属另一类需相关方批准的变更;资源平衡(B)通常会延长或维持工期,而非压缩。 Rationale:C is correct. The question describes fast-tracking: starting successor tasks before predecessor tasks are complete, increasing risk but reducing duration at no additional cost. Crashing (A) achieves schedule compression by adding resources, the costly option described. Scope reduction (D) is a different type of change requiring stakeholder approval. Resource levelling (B) typically extends or maintains the schedule, not compresses it.