矩阵型组织与资源协商 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-225

题目

一个预测型项目进行到一半,某职能经理未通知你就把你最好的团队成员调去另一个项目。最好的应对是什么?
Halfway through a predictive project, a functional manager pulls one of your best team members onto another initiative without telling you. What is the BEST response?

选项

  1. A.Immediately escalate to the sponsor and the PMO.
  2. B.Accept the loss and replan the schedule around it.
  3. C.Have a direct conversation with the functional manager about the impact and negotiate a solution.
  4. D.Ask the team member to secretly keep working on your project.
正确答案:C

解析

解析:在矩阵型组织中,项目经理与职能经理协商资源,因此应先就直接影响沟通。立即上报会跳过关系维护;默默承受等于放弃项目需求;要求暗中工作则让成员陷入两难。 Rationale:In a matrix organisation the PM negotiates resources with functional managers, so a direct conversation about impact comes first. Immediate escalation skips the relationship; absorbing the loss abandons project needs; covert work puts the member in an impossible position.