题目
一个预测型项目进行到一半,某职能经理未通知你就把你最好的团队成员调去另一个项目。最好的应对是什么?
Halfway through a predictive project, a functional manager pulls one of your best team members onto another initiative without telling you. What is the BEST response?
选项
- A.Immediately escalate to the sponsor and the PMO.
- B.Accept the loss and replan the schedule around it.
- C.Have a direct conversation with the functional manager about the impact and negotiate a solution.
- D.Ask the team member to secretly keep working on your project.
解析
解析:在矩阵型组织中,项目经理与职能经理协商资源,因此应先就直接影响沟通。立即上报会跳过关系维护;默默承受等于放弃项目需求;要求暗中工作则让成员陷入两难。
Rationale:In a matrix organisation the PM negotiates resources with functional managers, so a direct conversation about impact comes first. Immediate escalation skips the relationship; absorbing the loss abandons project needs; covert work puts the member in an impossible position.
同考点练习题
-
PMP202611-038 · 答案 B
-
PMP202611-146 · 答案 A
-
PMP202611-226 · 答案 A
-
PMP202611-254 · 答案 C
-
A functional manager keeps pulling your team members onto operational work. The BEST approach is to:PMP202611-495 · 答案 A