在弱矩阵型组织中,项目经理面临的主要挑战是什么?
What is the main challenge for a project manager in a Weak Matrix organization?
选项
- A.Full authority over the project budget
- B.Limited authority over team resources
- C.Team members working on only one project
- D.Full control by the PMO
解析
解析:在弱矩阵结构中,资源由职能经理掌控,项目经理的权限相对有限。
Rationale:In a weak matrix structure, functional managers control resources, leaving the project manager with limited authority.