某敏捷团队由刚合并的三家公司员工组成,各组都强烈认同原公司做法、抵触其他组的做法。Scrum Master 的首要任务是什么?
An agile team has been formed from employees across three different companies that recently merged. Each group has strong loyalty to their former company's practices and resists the other groups' approaches. What is the Scrum Master's priority?
选项
- A.Allow each subgroup to work independently using their preferred practices.
- B.Facilitate the co-creation of a new team working agreement that draws the best from all three cultures, building shared identity and mutual respect rather than imposing any one group's norms.
- C.Mandate the acquiring company's practices as the standard going forward.
- D.Escalate to leadership to resolve the cultural integration issue.
解析
解析:B 正确。并购后的团队融合是典型的仆人式领导挑战。共同制定工作协议能让各方对团队规范拥有所有权——规范不继承自任何一家公司,而属于新团队,这比强推标准更快建立共同身份。强推某一方(C)制造赢家与输家;各组独立(A)等于阻止团队形成;直接上报(D)跳过了 Scrum Master 的引导职责。
Rationale:B is correct. Post-merger team integration is a classic servant leadership challenge. Co-creating a working agreement gives all parties ownership of the team's norms: it is not inherited from any single company, it belongs to the new team. This builds shared identity faster than any imposed standard. Mandating one company's practices (C) creates winners and losers. Independent subgroups (A) prevents team formation entirely. Escalation (D) skips the Scrum Master's facilitation responsibility.