题目
敏捷环境下的项目经理发现团队常态性每周工作 50~60 小时、出现倦怠迹象,速率虽高但已在下降。应该怎么办?
A project manager working in an agile environment notices that team members are routinely working 50–60 hour weeks and showing signs of burnout. Velocity is high but declining. What should happen?
选项
- A.Address the unsustainable pace immediately. The Agile Manifesto principle of sustainable pace means the team should be able to maintain their current velocity indefinitely. Burnout causes velocity collapse. Reduce sprint commitments, investigate root causes and protect the team's wellbeing.
- B.Hire additional contractors to share the workload.
- C.Maintain the pace: high velocity is the goal and the team will recover after the release.
- D.Ask team members to take their time off after the project ends.
解析
解析:A 正确。敏捷宣言第 8 条明确写道:敏捷过程倡导可持续发展,发起人、开发者和用户应能无限期维持恒定节奏。倦怠既是伦理问题也是交付风险,速率下滑正是崩塌的前兆。继续硬撑(C)是以团队健康和长期交付换取短期产出;延后补偿(D)与增聘外包(B)都没有触及系统性的节奏问题。
Rationale:A is correct. The Agile Manifesto's 8th principle explicitly states: "Agile processes promote sustainable development. The sponsors, developers, and users should be able to maintain a constant pace indefinitely." Burnout is both an ethical issue and a delivery risk: declining velocity is the leading indicator of impending collapse. Continuing the pace (C) maximises short-term output at the cost of team health and long-term delivery. Deferred recovery (D) and contractor hire (B) don't address the systemic pace problem.