某团队实践持续交付,每天多次发布软件。一次发布引发了生产事故。为管理该风险,最重要的能力是什么?
A team practising continuous delivery releases software multiple times per day. A release causes a production incident. What is the most important capability needed to manage this risk?
选项
- A.Stop continuous delivery and revert to scheduled monthly releases.
- B.A robust automated rollback capability and fast incident response process, the ability to recover quickly matters more than preventing every possible issue.
- C.A longer testing phase before each release to prevent incidents.
- D.Assign a dedicated QA team to approve every release before it goes live.
解析
解析:B 正确。在高频部署下,目标不是零事故(这不可能),而是快速恢复:平均恢复时间(MTTR)比平均故障间隔(MTBF)更重要。自动化回滚与事故响应是关键使能项。加长测试阶段(C)与高频发布模式相冲突;回到按月发布(A)等于放弃该交付模式;人工 QA 关卡(D)形成与持续交付不兼容的瓶颈。
Rationale:B is correct. In continuous delivery environments, the goal is not zero incidents (impossible at high deployment frequency) but fast recovery. Mean Time to Recovery (MTTR) matters more than Mean Time Between Failures (MTBF). Automated rollback and incident response capabilities are the key enablers. A longer testing phase (C) contradicts the high-frequency release model. Reverting to monthly releases (A) abandons the delivery model. Manual QA gates (D) create a bottleneck incompatible with continuous delivery.