完成定义 DoD · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-301

题目

某敏捷团队把用户故事的“完成”定义为:代码完成、单元测试通过、同行评审通过。多个冲刺之后,运维团队在发布后不断发现集成问题。团队应该改变什么?
An agile team defines "Done" for a user story as: code complete, unit tested and peer-reviewed. After multiple sprints, the operations team keeps finding integration issues post-release. What should the team change?

选项

  1. A.The current DoD is sufficient: integration issues are expected in agile delivery.
  2. B.Expand the Definition of Done to include integration testing and operational readiness checks, and involve the operations team in defining these criteria.
  3. C.Add a separate post-release testing phase to catch integration issues before they reach operations.
  4. D.The operations team should improve their own processes rather than blame the development team.
正确答案:B

解析

解析:B 正确。完成定义应随团队认知演进。发布后反复出现运维问题,明确说明 DoD 不完整。让运维参与扩展 DoD,能形成共同责任并在冲刺内验证集成就绪。责怪运维(D)无视系统性缺口;增加发布后阶段(C)把测试移出冲刺,等于造了个小瀑布;成熟敏捷交付并不把集成问题视为常态(A)。 Rationale:B is correct. The Definition of Done should evolve as the team learns. Recurring operational issues after release are a clear signal that the DoD is incomplete. Involving operations in expanding the DoD creates shared ownership and ensures integration readiness is verified within the sprint. Blaming operations (D) ignores the systemic gap. A post-release phase (C) moves testing outside the sprint, creating a mini-waterfall. Integration issues are not an accepted norm in mature agile delivery (A).