题目
某团队采用 SAFe。项目群增量(PI)计划会刚结束,识别出两个团队之间的关键依赖,但尚未明确负责人。应该怎么处理?
A team is using SAFe (Scaled Agile Framework). The Programme Increment (PI) Planning has just completed. A critical dependency between two teams is identified but no clear owner has been assigned. What should happen?
选项
- A.Record the dependency in the PI Planning board and resolve it during the next PI retrospective.
- B.Continue PI planning and address unowned dependencies after planning concludes.
- C.Assign the dependency to the Release Train Engineer to manage on behalf of both teams.
- D.Immediately identify an owner for the dependency, record it on the programme board, and ensure both teams have a clear agreement on how it will be managed throughout the PI.
解析
解析:D 正确。在规模化敏捷交付中,无人管理的跨团队依赖属于最高风险之一。PI 计划会正是为识别与规划依赖而设计,因此在计划结束前必须解决无主依赖:明确负责人并促成团队间共识。拖到回顾会(A)太晚;RTE(C)负责促进,不应包揽所有依赖;不解决就继续(B)正是多数 PI 失败的主因。
Rationale:D is correct. Unmanaged cross-team dependencies are among the highest risks in scaled agile delivery. PI Planning is specifically designed to identify and plan dependencies. Any dependency without an owner during planning must be resolved before planning concludes: assigning clear ownership and inter-team agreement is the goal. Deferring to a retrospective (A) is too late. The RTE (C) facilitates but shouldn't own every dependency. Continuing without resolution (B) is the root cause of most PI failures.