技术实践与持续交付 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-293

题目

某开发团队能完成全部冲刺待办事项,却无法交付可发布的增量,因为集成测试总在冲刺末失败。根因与最佳解决方案是什么?
A development team completes all sprint backlog items but cannot deliver a potentially shippable increment because integration testing always fails at the end of the sprint. What is the root cause and best solution?

选项

  1. A.Extend the sprint by one week to allow time for integration testing.
  2. B.Add a dedicated testing sprint after each development sprint.
  3. C.Integration testing is happening too late: move testing activities throughout the sprint using continuous integration and shift-left testing practices.
  4. D.Remove integration testing from the Definition of Done to enable sprint completion.
正确答案:C

解析

解析:C 正确。冲刺末集成失败是“敏捷外壳里的瀑布”的典型症状。解法是持续集成:在整个冲刺中持续集成与测试,而不是末尾一次性做,这是敏捷的基本工程实践。延长冲刺(A)治标不治本;加固冲刺(B)属反模式,违背可持续节奏;把测试移出完成定义(D)会制造技术债并放行缺陷。 Rationale:C is correct. End-of-sprint integration failures are a classic sign of waterfall-within-agile. The solution is continuous integration: integrating and testing continuously throughout the sprint rather than batching at the end. This is a fundamental agile engineering practice. Extending sprints (A) doesn't fix the root cause. Hardening sprints (B) are an anti-pattern that undermines the sustainable pace principle. Removing testing from the DoD (D) creates technical debt and ships defects.

同考点练习题