某开发团队能完成全部冲刺待办事项,却无法交付可发布的增量,因为集成测试总在冲刺末失败。根因与最佳解决方案是什么?
A development team completes all sprint backlog items but cannot deliver a potentially shippable increment because integration testing always fails at the end of the sprint. What is the root cause and best solution?
选项
- A.Extend the sprint by one week to allow time for integration testing.
- B.Add a dedicated testing sprint after each development sprint.
- C.Integration testing is happening too late: move testing activities throughout the sprint using continuous integration and shift-left testing practices.
- D.Remove integration testing from the Definition of Done to enable sprint completion.
解析
解析:C 正确。冲刺末集成失败是“敏捷外壳里的瀑布”的典型症状。解法是持续集成:在整个冲刺中持续集成与测试,而不是末尾一次性做,这是敏捷的基本工程实践。延长冲刺(A)治标不治本;加固冲刺(B)属反模式,违背可持续节奏;把测试移出完成定义(D)会制造技术债并放行缺陷。
Rationale:C is correct. End-of-sprint integration failures are a classic sign of waterfall-within-agile. The solution is continuous integration: integrating and testing continuously throughout the sprint rather than batching at the end. This is a fundamental agile engineering practice. Extending sprints (A) doesn't fix the root cause. Hardening sprints (B) are an anti-pattern that undermines the sustainable pace principle. Removing testing from the DoD (D) creates technical debt and ships defects.