题目
冲刺计划中,团队把某用户故事估算为 13 个故事点。产品负责人说“看起来没那么复杂”,应该是 5 个。应该怎么处理?
During sprint planning, the team estimates a user story at 13 story points. The Product Owner says it should be 5 because "it doesn't seem that complex." What should happen?
选项
- A.Accept the PO's estimate. They are accountable for the backlog and its prioritisation.
- B.The development team owns the estimates. The PO should explain any misunderstandings about the story, but the final effort estimate belongs to the team doing the work.
- C.Split the difference and estimate at 8 story points as a compromise.
- D.Ask the Scrum Master to decide the final estimate.
解析
解析:B 正确。在 Scrum 中,估算是开发团队(真正做事的人)独有的责任。产品负责人可以澄清需求、补充信息或把故事拆小,但不能推翻团队的工作量估算。随意折中(C)损害估算的严肃性;Scrum Master(D)同样不做估算,只做引导。
Rationale:B is correct. In Scrum, estimation is the sole responsibility of the development team, the people who will do the work. The PO may clarify requirements, provide missing information, or split the story into smaller pieces, but cannot override the team's effort estimate. Arbitrary compromise (C) undermines estimation integrity. The Scrum Master (D) also does not estimate. They facilitate.