职业道德与合规 中等 Business Environment 商业环境域 题号 PMP202611-499

题目

两个部门都声称对某交付物拥有主导权,冲突正向高层升级。项目经理最恰当的动作是:
Two departments both claim ownership of a deliverable and the conflict is escalating to executives. The project manager's BEST move is to:

选项

  1. A.Pick a side quickly to end the debate
  2. B.Let executives decide without input
  3. C.Split the deliverable arbitrarily
  4. D.Facilitate a joint session to clarify accountability using the project charter and RACI
正确答案:D

解析

解析:用章程与 RACI 共同澄清,是把归属问题按结构解决,而不是搞政治平衡。 Rationale:Facilitating a joint clarification using the charter and RACI resolves ownership structurally rather than politically.