题目
两个部门都声称对某交付物拥有主导权,冲突正向高层升级。项目经理最恰当的动作是:
Two departments both claim ownership of a deliverable and the conflict is escalating to executives. The project manager's BEST move is to:
选项
- A.Pick a side quickly to end the debate
- B.Let executives decide without input
- C.Split the deliverable arbitrarily
- D.Facilitate a joint session to clarify accountability using the project charter and RACI
解析
解析:用章程与 RACI 共同澄清,是把归属问题按结构解决,而不是搞政治平衡。
Rationale:Facilitating a joint clarification using the charter and RACI resolves ownership structurally rather than politically.
同考点练习题
-
PMP202611-030 · 答案 B
-
PMP202611-232 · 答案 A
-
PMP202611-248 · 答案 C
-
PMP202611-277 · 答案 A
-
PMP202611-331 · 答案 A
-
PMP202611-370 · 答案 D
-
PMP202611-481 · 答案 B