题目
你虚拟团队中的一位关键贡献者时区早六小时,因会议总按多数人方便的时段安排而正在悄然抽离。项目经理应该怎么做?
A key contributor on your virtual team is six hours ahead and is quietly disengaging because meetings are always at hours convenient for the majority. What should the project manager do?
选项
- A.Rotate meeting times and lean on asynchronous updates so the burden is shared fairly.
- B.Tell the contributor that occasional inconvenient hours are part of the job.
- C.Record meetings so the contributor can watch later instead of attending.
- D.Move the contributor to lower-priority work that needs fewer meetings.
解析
解析:轮换时段并配合异步协作,把不便公平分摊,也传递出包容信号,有助于维持分布式团队投入度。让人默默接受忽视了本可修正的不公;只靠录播会加深孤立;把其边缘化则是让成员为项目经理造成的排期问题买单。
Rationale:Rotating times and using asynchronous work shares the inconvenience and signals inclusion, which keeps a distributed team engaged. Telling them to accept it ignores a fixable inequity; recording alone deepens isolation; sidelining them penalises them for a scheduling problem the PM created.