题目
项目规划阶段遗漏了一项关键监管要求。项目经理首先应该做什么?
A key regulatory requirement was missed during project planning. What should the project manager do first?
选项
- A.Update the risk register
- B.Submit a change request
- C.Inform the sponsor
- D.Analyze the impact on project objectives
解析
解析:在提出变更或上报之前,项目经理必须先分析其对范围、进度和成本的影响。
Rationale:Before initiating changes or escalation, the PM must first analyze the impact on scope, schedule, and cost.