识别相关方与登记册 · PMP 练习题解析

相关方管理 简单 People 人域 题号 PMP202611-086

题目

你正在为项目收集需求。你可能会将相关方登记册用于以下所有用途,除了:
You are involved in collecting requirements for your project. You are likely to use the stakeholder register for all of the following EXCEPT:

选项

  1. A.Identifying stakeholders who can provide information on the requirements
  2. B.Capturing major requirements that stakeholders may have for the project
  3. C.Capturing main expectations that stakeholders may have for the project
  4. D.Evaluating the product breakdown structure (PBS) associated with each of the key stakeholders
正确答案:D

解析

解析:相关方登记册用于识别谁能提供需求信息,并记录其需求与期望。产品分解结构属于范围管理工具,并不是登记册要逐位相关方去评估的对象。 Rationale:The stakeholder register identifies who can provide requirement information and captures their requirements and expectations. A product breakdown structure is a scope artifact, not something the register is used to evaluate per stakeholder.