范围管理 中等 Process 过程域 题号 PMP202611-604

题目

发起人索要一份包含产品需求的描述、责任人、来源、优先级与状态的文件。他要的是哪一份?
The sponsor asks for a copy of the document that contains the description, owner, source, priority and status of product requirements. Which document is being requested?

选项

  1. A.The requirements management plan
  2. B.The requirements traceability matrix
  3. C.The scope management plan
  4. D.The work breakdown structure (WBS)
正确答案:B

解析

解析:需求追溯矩阵把需求与其来源、对应交付物连接起来,属性包括编号、描述、责任人、来源、优先级、版本与状态。 Rationale:The requirements traceability matrix links requirements to their origin and to deliverables, with attributes such as ID, description, owner, source, priority, version and status.