质量控制与检查 · PMP 练习题解析

质量管理 中等 Process 过程域 题号 PMP202611-603

题目

你在管理一个 IT 基础设施项目,监控“按时完成任务占比”“每日缺陷数”“变更请求数量”等指标。如何判断项目是否达标?
You manage an IT infrastructure project monitored for indicators such as percentage of tasks completed on time, defects per day, and number of change requests. How will you know if your project is compliant with these indicators?

选项

  1. A.By comparing the results to the quality management plan
  2. B.By reviewing the audit report
  3. C.By comparing the results to the quality metrics
  4. D.By using quality analysis
正确答案:C

解析

解析:质量量度规定了测什么以及可接受的波动范围;达标与否就是把实际结果与它比对。 Rationale:Quality metrics define what will be measured and the acceptable range of variation; compliance is judged by comparing actual results to them.