题目
项目预算含 10% 管理储备与 15% 应急储备。执行中一个已识别的风险发生了,应动用哪项储备?
A project has a budget with a 10% management reserve and a 15% contingency reserve. During execution, an identified risk materialises. Which reserve should be used?
选项
- A.Neither: identified risks should be funded through scope reduction.
- B.Management reserve: it is the larger of the two reserves.
- C.Contingency reserve. It is specifically allocated for identified risks that materialise. Management reserve is for unknown unknowns (unk-unks) and requires sponsor/senior management approval to access.
- D.Either reserve, the PM chooses based on which has more funds available.
解析
解析:C 正确。应急储备针对“已知—未知”:已识别且有应对计划的风险,由项目经理掌控。管理储备针对“未知—未知”,即完全未预见的事件,由高层或发起人掌控。正确动用储备是 PMBOK 的关键概念。金额大小(B)与适用性无关;储备各有专门用途,不能由项目经理随意挑(D);削减范围(A)是另一种更激进的应对。
Rationale:C is correct. Contingency reserve is for "known unknowns": identified risks with documented response plans. It is controlled by the project manager. Management reserve is for "unknown unknowns", completely unforeseen events, and is controlled by senior management or the sponsor. Using reserves correctly is a key PMBOK concept. Size (B) is irrelevant to which reserve is appropriate. Reserves have specific purposes, not PM discretion (D). Scope reduction (A) is a separate and more drastic response.