团队交付一直不错,但有一名成员承担越来越多、正走向倦怠,而其他人还有余力。最合适的行动是什么?
Your team has been delivering well, but one member is taking on more and more, heading toward burnout, while others have spare capacity. What is the most appropriate action?
选项
- A.Praise the overloaded member publicly for their dedication.
- B.Wait to see if the member raises it themselves before acting.
- C.Quietly reassign the member's tasks without telling anyone.
- D.Talk with the team about workload balance and help redistribute the work.
解析
解析:服务型领导要保护团队可持续的节奏,因此应公开讨论工作量并与团队一起重新平衡。公开表扬等于奖励超负荷;等待则有倦怠风险;私自转走任务剥夺了成员的自主性。
Rationale:Servant leadership protects the team's sustainable pace, so you address workload openly and rebalance with the team. Public praise rewards the overload; waiting risks burnout; silent reassignment removes the member's agency.