题目
项目经理正在编制质量管理计划。项目涉及零部件制造,而缺陷在量产后修复代价极高。哪种质量策略最合适?
A project manager is developing a quality management plan. The project involves manufacturing components where defects are very costly to fix post-production. Which quality approach is most appropriate?
选项
- A.Quality control only: inspect finished components and reject defective ones.
- B.Quality assurance: build quality into the process through standards, audits and process improvements to prevent defects before they occur.
- C.Accept a reasonable defect rate and manage costs through warranty claims.
- D.Outsource quality management to the manufacturing vendor.
解析
解析:B 正确。量产后修复缺陷代价高昂时,预防永远比检验更经济。质量保证以预防为导向,把质量建进流程,阻止缺陷发生。质量控制(A,检验导向)只能在缺陷产生后筛出,对高代价制造而言太晚。质量成本原则是:预防成本 < 评估成本 < 失败成本。接受缺陷率(C)与外包责任(D)都等于放弃质量治理。
Rationale:B is correct. When defects are expensive to fix post-production, prevention is always more cost-effective than inspection. Quality assurance (prevention-focused) builds quality into processes to stop defects from occurring. Quality control (inspection-focused, option A) catches defects after they are made: too late for costly manufacturing. The cost of quality principle states: prevention costs less than appraisal, which costs less than failure. Accepting defect rates (C) and outsourcing accountability (D) both abandon quality governance.