敏捷与预测方法论选择 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-233

题目

你正在领导一个混合型项目:用户界面需求不确定且可能变化,而后端集成清晰稳定。你应如何裁剪方法?
You are leading a hybrid project. The user interface requirements are uncertain and likely to change, while the back-end integration is well understood and stable. How should you tailor the approach?

选项

  1. A.Use an agile, iterative approach for the UI and a predictive approach for the stable back-end.
  2. B.Use a fully predictive approach for the whole project.
  3. C.Use a fully agile approach for the whole project.
  4. D.Wait until all requirements are clear, then plan predictively.
正确答案:A

解析

解析:裁剪就是在不确定性高之处用敏捷、在工作稳定之处用预测型,这正是混合方法的价值。全预测型难以应对界面变化;全敏结对稳定工作增加了不必要的仪式;等需求完全清晰则会拖住项目。 Rationale:Tailoring applies agile where uncertainty is high and predictive where work is stable, which is exactly what hybrid is for. A fully predictive plan handles the uncertain UI poorly; a fully agile approach adds unnecessary ceremony to stable work; waiting for full clarity stalls the project.