定量风险分析:EMV与决策树 · PMP 练习题解析

风险管理 中等 Process 过程域 题号 PMP202611-471

题目

某风险发生概率 30%,影响金额 2 万美元。其预期货币价值(EMV)是多少?
A risk has a 30% probability and a $20,000 impact. What is its expected monetary value (EMV)?

选项

  1. A.$50,000
  2. B.$14,000
  3. C.$6,000
  4. D.$26,000
正确答案:C

解析

解析:EMV = 概率 × 影响 = 0.30 × 20000 = 6000 美元。 Rationale:EMV = probability × impact = 0.30 × $20,000 = $6,000.