在定量风险分析中,哪种工具有助于确定哪些风险对项目结果影响最大?
During quantitative risk analysis, which tool helps determine which risks have the greatest impact on project outcomes?
选项
- A.Probability and Impact Matrix
- B.Tornado Diagram
- C.SWOT Analysis
- D.Risk Register
解析
解析:龙卷风图可以直观展示哪些变量对项目结果的影响最大。
Rationale:A Tornado Diagram visually shows which variables have the most influence on project outcomes.