风险决策 · PMP 练习题解析

首页 › Process 过程域 › 风险管理 › 风险决策 › PMP202611-137
风险管理 困难 Process 过程域 题号 PMP202611-137

题目

某营销 App 团队刚上线用户上传照片的功能。由内容审核员审核照片,但管理层担心人为失误,建议引入第三方 AI 工具辅助。项目经理应该怎么做?
A marketing app team recently launched a feature allowing users to upload photos. A content moderator reviews the photos, but management is concerned about human error and suggests using a third-party AI tool to assist. What should the project manager do?

选项

  1. A.Ask the AI tool provider to present product specifics regarding content moderation
  2. B.Review the risk management plan for risks related to content moderation and ensure the plan is current
  3. C.Determine the cost and accuracy of using the AI tool to support content moderation
  4. D.Perform a risk analysis to understand the likelihood and impact of an issue related to content moderation
正确答案:D

解析

解析:发现新的风险或相关方担忧时,应先分析风险再决定是否采用某个方案。评估发生概率与影响才能确定真实风险敞口,之后才谈得上 AI 工具这类应对措施是否有必要、是否划算。 Rationale:When a new risk or stakeholder concern is identified, the project manager must analyze it before adopting a proposed solution. Assessing probability and impact establishes true exposure; only then can the team judge whether a risk response such as the AI tool is necessary and cost-effective.