题目
指导资历较浅的团队成员属于哪类项目管理活动?
Mentoring a junior team member is an example of which project management activity?
选项
- A.Risk management
- B.Procurement
- C.Team development
- D.Scope validation
解析
解析:辅导能提升团队能力,是 People 领域“建设团队”的核心动作。
Rationale:Mentoring develops team competency — a core part of developing the team in the People domain.