质量管理 中等 Process 过程域 题号 PMP202611-398

题目

项目经理审计时发现,团队为缓解进度压力已连续三个月绕过质量保证流程,多项交付物未经正规评审就被批准。当务之急是什么?
A project manager is conducting a project audit and discovers that the team has been bypassing the quality assurance process for three months to meet schedule pressure. Several deliverables have been approved without proper review. What is the immediate priority?

选项

  1. A.Report the findings to the appropriate authority, assess the risk of defects in already-delivered work, determine whether retrospective QA is required for critical deliverables, and restore the quality process immediately.
  2. B.Quietly reinstate the quality process without disclosing the past bypass to avoid alarming stakeholders.
  3. C.Continue the project and implement the quality process from this point forward.
  4. D.Discipline the team members who bypassed the process.
正确答案:A

解析

解析:A 正确。系统性绕过质量流程是严重的治理与风险问题,需要透明上报、评估既有交付物的风险,并立即恢复流程。相关方可能正依赖未经正规评审的成果。不披露就继续(C、B)等于让风险持续存在;处分(D)只处理人的维度而不解决产品风险,且在弄清进度压力是否源于管理层造成的系统性问题之前就处分,可能为时过早。 Rationale:A is correct. A systematic quality bypass is a serious governance and risk issue requiring transparent reporting, risk assessment of existing deliverables and immediate process restoration. Stakeholders may be relying on deliverables that have not been properly reviewed. Continuing without disclosure (C, B) perpetuates a risk that stakeholders deserve to know about. Discipline (D) addresses the personnel dimension but not the product risk, and may be premature before understanding whether schedule pressure was a systemic issue that management caused.