题目
某 Scrum 团队每个冲刺都交付可运行增量,但组织的发布流程需要 6 周才能部署上线。这违反了什么敏捷原则,应改进什么?
A Scrum team delivers a working increment every sprint but the organisation's release process takes 6 weeks to deploy. What agile principle is being violated and what should be improved?
选项
- A.No principle is violated, the team is delivering working increments as required.
- B.The team should stop delivering increments and batch work into 6-week releases.
- C.Sprint length should be extended to 6 weeks to match the release cycle.
- D.The principle of delivering working software frequently and getting rapid customer feedback is violated by the 6-week release cycle. The release process should be automated and streamlined to enable frequent production deployments.
解析
解析:D 正确。6 周才部署意味着每个冲刺后客户反馈要延迟 6 周以上,敏捷价值被大幅抵消。敏捷宣言主张频繁地把可运行软件交付给真实用户。瓶颈在发布流程(而非团队),所以应通过自动化(CI/CD 流水线)精简流程。延长冲刺(C)只会让团队更不灵敏;批量发布(B)彻底取消了增量交付。
Rationale:D is correct. A 6-week deployment delay means customer feedback is delayed by 6+ weeks after each sprint: negating much of agile's value. The Agile Manifesto prioritises frequent delivery of working software to real users. The bottleneck is the release process (not the team), so the fix is to streamline it through automation (CI/CD pipelines). Extending sprints (C) makes the team less responsive. Batching releases (B) eliminates incremental delivery entirely.