题目
小型隧道掘进机原型测试中,团队发现原测试设备必须加装新探头,将显著抬高项目成本。下一步应当做什么?
During tests of a small-scale tunnel boring machine prototype, the team finds the original test equipment must be upgraded with new probes, substantially increasing project cost. What is your next step?
选项
- A.Identify the full extent of the changes needed, and update the change management plan to reflect these changes
- B.Find out the cost of new test gear and then hide the cost difference by economizing in other activities
- C.Determine the cost of the new components, and submit a change request to update the cost baseline
- D.Review the requirements traceability matrix to understand why the original test equipment was insufficient
解析
解析:题干点明的影响是成本:先算清差额,再走变更控制修改成本基准,而不是私下从别处腾挪。
Rationale:The highlighted impact is cost: determine the difference, then follow change control to modify the cost baseline rather than quietly offsetting it elsewhere.
同考点练习题
-
PMP202611-101 · 答案 B
-
PMP202611-337 · 答案 B
-
PMP202611-423 · 答案 A