成本控制与诚信 · PMP 练习题解析

成本管理 困难 Process 过程域 题号 PMP202611-602

题目

小型隧道掘进机原型测试中,团队发现原测试设备必须加装新探头,将显著抬高项目成本。下一步应当做什么?
During tests of a small-scale tunnel boring machine prototype, the team finds the original test equipment must be upgraded with new probes, substantially increasing project cost. What is your next step?

选项

  1. A.Identify the full extent of the changes needed, and update the change management plan to reflect these changes
  2. B.Find out the cost of new test gear and then hide the cost difference by economizing in other activities
  3. C.Determine the cost of the new components, and submit a change request to update the cost baseline
  4. D.Review the requirements traceability matrix to understand why the original test equipment was insufficient
正确答案:C

解析

解析:题干点明的影响是成本:先算清差额,再走变更控制修改成本基准,而不是私下从别处腾挪。 Rationale:The highlighted impact is cost: determine the difference, then follow change control to modify the cost baseline rather than quietly offsetting it elsewhere.