进度管理 中等 Process 过程域 题号 PMP202611-113

题目

以下哪项属于强制性依赖关系?
Which of the following is an example of a mandatory dependency?

选项

  1. A.A dependency developed based on knowledge of best practices in a certain application area
  2. B.A dependency formed because of an unusual project element that requires a certain sequencing
  3. C.Erecting the superstructure only after the foundation has been completed on a construction project
  4. D.On a software project, starting design only after all requirements are completed and approved
正确答案:C

解析

解析:强制性依赖源于法律、合同或工作的物理特性,例如必须先完成地基才能建造上部结构。基于最佳实践或偏好顺序的依赖属于选择性依赖(软逻辑)。 Rationale:Mandatory dependencies are legally, contractually, or physically inherent in the work—such as building the superstructure only after the foundation. Best-practice or preferred sequencing is discretionary (soft logic).