项目经理正在编制工作分解结构(WBS)。一名成员建议把“召开会议”“发送邮件”这类活动也纳入 WBS。正确做法是什么?
A project manager is developing a WBS. A team member suggests including activities (like "conduct meeting" or "send email") in the WBS. What is the correct approach?
选项
- A.Include activities only for work packages that are high-risk.
- B.Include activities, the more detailed the WBS, the better the project control.
- C.The WBS should contain deliverables and work packages, not activities. Activities belong in the activity list and schedule, not the WBS.
- D.Combine deliverables and activities in the WBS for a more complete picture.
解析
解析:C 正确。WBS 把项目范围分解为可交付成果与工作包,是面向成果而非面向活动的。活动在进度规划阶段单独列入活动清单,不属于 WBS。把活动写进 WBS 是常见错误,会混淆范围定义与进度规划。WBS 的最底层是工作包,再由工作包识别出活动。
Rationale:C is correct. The WBS decomposes the project scope into deliverables and work packages. It is deliverable-oriented, not activity-oriented. Activities are defined separately in the activity list during schedule planning and are not part of the WBS. Including activities in the WBS is a common mistake that creates confusion between scope definition and schedule planning. The lowest level of the WBS is the work package, from which activities are then identified.