定义活动与活动清单 · PMP 练习题解析

进度管理 简单 Process 过程域 题号 PMP202611-300

题目

项目经理正在编制工作分解结构(WBS)。一名成员建议把“召开会议”“发送邮件”这类活动也纳入 WBS。正确做法是什么?
A project manager is developing a WBS. A team member suggests including activities (like "conduct meeting" or "send email") in the WBS. What is the correct approach?

选项

  1. A.Include activities only for work packages that are high-risk.
  2. B.Include activities, the more detailed the WBS, the better the project control.
  3. C.The WBS should contain deliverables and work packages, not activities. Activities belong in the activity list and schedule, not the WBS.
  4. D.Combine deliverables and activities in the WBS for a more complete picture.
正确答案:C

解析

解析:C 正确。WBS 把项目范围分解为可交付成果与工作包,是面向成果而非面向活动的。活动在进度规划阶段单独列入活动清单,不属于 WBS。把活动写进 WBS 是常见错误,会混淆范围定义与进度规划。WBS 的最底层是工作包,再由工作包识别出活动。 Rationale:C is correct. The WBS decomposes the project scope into deliverables and work packages. It is deliverable-oriented, not activity-oriented. Activities are defined separately in the activity list during schedule planning and are not part of the WBS. Including activities in the WBS is a common mistake that creates confusion between scope definition and schedule planning. The lowest level of the WBS is the work package, from which activities are then identified.

同考点练习题