进度管理 困难 Process 过程域 题号 PMP202611-486

题目

甘特图主要展示:
A Gantt chart primarily displays:

选项

  1. A.Risk probabilities
  2. B.Activities plotted against a timeline
  3. C.Team skills
  4. D.Budget variance
正确答案:B

解析

解析:甘特图用条形把活动铺在日历时间轴上。 Rationale:Gantt charts show scheduled activities as bars against calendar time.